How should IT plan a change freeze over the Christmas and New Year holidays?
· 4 min read
Agree the year-end change freeze with the business in writing, define the exceptions and approver, publish the schedule early and staff the holidays properly.
In brief
A change freeze over Christmas and New Year works best as a written agreement with the business rather than an informal rule. Decide which services it covers, the exact start and end dates, what can still go ahead and who can approve an exception while people are on leave. Typical exceptions are proven standard changes, security fixes for actively exploited vulnerabilities and fixes for major incidents. Publish the change schedule early so clashes show up in November, and set a cut off for change requests well before the freeze so the last week does not become the busiest of the year. Check supplier end of support dates, renewals and vendor switchovers that fall in the holiday period and plan them as scheduled changes. Keep emergency changes honest by logging every exception and reviewing the list in January. Staff the freeze like an incident period, with on call cover, escalation contacts and supplier support hours for every day. Use the quieter weeks for documentation, knowledge articles and clearing old tickets, then lift the freeze one service at a time. The article draws on John Sansbury's The Journey to Service Excellence.
Plan the freeze as an agreement with the business, not a lock on the door: decide which services it covers, the exact dates, what can still go ahead and who can approve an exception. Then use the quieter weeks for low risk work you never get to, and make sure the people who might be needed are actually reachable.
Why year-end freezes go wrong
Most teams freeze change in December for a good reason. Fewer staff are around, many businesses are at a peak, and a failed change is harder to fix when the people who understand it are on leave. John Sansbury puts the logic plainly in The Journey to Service Excellence: "the most effective way to minimise the negative impact of change is to agree a change freeze, as usually happens at peak business periods."
The trouble starts when the freeze is a date in someone's head rather than a written agreement. Projects with year-end deadlines try to squeeze in just before it starts, supplier deadlines and certificate renewals land in the middle of it, and anything that has to happen anyway gets labelled an emergency. The result can be more risk in December, not less.
Practical steps
- Agree scope and dates with the business now. Name the services covered, the start and end dates and times, and any services that stay open for change because they are quiet over the holidays. Write it into your change policy or a short freeze notice, and get it signed off by the people who own those services.
- Define what is still allowed. Pre-approved standard changes with a proven procedure, security fixes for actively exploited vulnerabilities and fixes for major incidents are the usual exceptions. Everything else waits. Say who approves an exception during the freeze, and make sure that person is on the rota.
- Keep emergencies honest. A freeze tempts people to relabel planned work as urgent. John's warning applies directly: "Emergency changes should never be used as a proxy for an ‘urgent’ change, which simply implies a lack of planning." Log every exception, and review the list in January.
- Publish the change schedule early. John describes two purposes for the change schedule: "to prepare consumers for the impact of the change and to encourage anyone that may know of a reason why the change should not proceed to speak up". Show the pre-freeze rush, the freeze itself and the first weeks of January in one place, so clashes surface in November, not on 22 December.
- Check external dates. List supplier end-of-support dates, licence and certificate renewals, and vendor product switchovers that fall between now and mid-January. Bring forward what you can, and plan the rest as scheduled changes with named owners.
- Avoid the pre-freeze stampede. Set a cut-off for change requests about two weeks before the freeze, and do not let the last week before it become the busiest week of the year. A change pushed through to beat the deadline is often the one that fails over the holidays.
- Staff it like an incident. Agree on-call cover, escalation contacts and supplier support hours for every day of the freeze, including the bank holidays. A freeze reduces change; it does not stop incidents.
- Use the quiet time well. Documentation, knowledge articles, clearing old tickets, reviewing standard change procedures and tidying configuration records are all low risk and pay off in January.
A short worked example
This is an illustrative example, not a real case. A regional housing association runs IT, facilities and HR services from one platform. In early November the change manager agrees a freeze from 19 December to 5 January covering the tenant portal, payroll and finance systems. Payroll has a run on 23 December, so payroll changes close on 5 December. The team finds that a supplier is retiring an old version of its integration on 31 December, so that upgrade is scheduled for 2 December with a tested remediation plan. During the freeze one exception is approved, a security patch, and it is logged. In January the team reviews the log, closes 140 stale tickets cleared during the quiet weeks and lifts the freeze one service at a time.
Common mistakes
- Freezing everything for everyone, which pushes people to work around the process.
- Forgetting non-IT changes. HR, facilities and finance changes to shared systems need the same rules.
- No named approver for exceptions, so either nothing gets fixed or anything gets through.
- Ending the freeze with a big bang, where every postponed change goes in on the first Monday of January.
- Ignoring supplier changes made to your services during the freeze.
Where this fits
This sits within change enablement, alongside release and service level management, and it applies well beyond IT. For more on ESM's Exchange, read using a change schedule to protect services and standard, normal and emergency changes, and share how your team handles the holidays in the Incident and problem space.
For the underlying good practice, see PeopleCert's ITIL guidance on change enablement and the service management standard ISO/IEC 20000.
If this helped, John Sansbury's The Journey to Service Excellence covers operational change, release policy and the change schedule in depth, and is available to Exchange members.
Tags: esm-questions, change-enablement, change-freeze, change-schedule, release-management
Sources
Join the Exchange free
Join free to unlock the complete knowledge library.
Founder membership is free for life
More from Esm
How do I upgrade my ITIL 4 certification to ITIL 5?
4 min read
AI usage limits at work: expected to use AI, then rationed
5 min read
How should a small team run a staging site without losing live content?
5 min read
Audience rules for individual articles
1 min read
Bring legacy articles across carefully
1 min read
Setting the audience for a whole knowledge base
1 min read
Related articles
How do I upgrade my ITIL 4 certification to ITIL 5?
How to move from ITIL 4 to ITIL (Version 5) without starting again: which single module upgrades each ITIL 4 designation, what the Bridge is for, and the 2027 dates to plan around.

AI usage limits at work: expected to use AI, then rationed
Workday research finds half of AI users hit usage limits last month, and the people with AI written into their performance expectations ran out most often. What leaders can do about the mixed message.
How should a small team run a staging site without losing live content?
Keep live as the source of truth for content and staging as the source of truth for code, move each one way only, and release from version control with a backup.
Audience rules for individual articles
Most articles should follow the audience rules of the knowledge base they live in. When an article deserves a rule of its own, and how to keep those rules few and explained.
Bring legacy articles across carefully
Moving to a new knowledge base? Bring the old articles across carefully, or bring the old problems with them. How to sort what to keep, fix and leave behind.
Setting the audience for a whole knowledge base
Most audience decisions in knowledge are made once, for a whole knowledge base, and then forgotten. Why that one setting deserves a deliberate answer and a regular check.