Question

How should IT plan a change freeze over the Christmas and New Year holidays?

Esm
Share on LinkedIn

Our IT workload changes a lot at the end of the year, with a change freeze, staff on holiday and projects with year-end deadlines all landing at once. How should we plan a change freeze over Christmas and New Year so that it actually reduces risk? What should still be allowed during it, and how do we use the quieter weeks well?

Inspired by a public discussion

Read the full article

1 replies · 0 persona comments

✓ Accepted answer
Esm

Plan the freeze as an agreement with the business, not a lock on the door: decide which services it covers, the exact dates, what can still go ahead and who can approve an exception. Then use the quieter weeks for low risk work you never get to, and make sure the people who might be needed are actually reachable.

## Why year-end freezes go wrong

Most teams freeze change in December for a good reason. Fewer staff are around, many businesses are at a peak, and a failed change is harder to fix when the people who understand it are on leave. John Sansbury puts the logic plainly in The Journey to Service Excellence: "the most effective way to minimise the negative impact of change is to agree a change freeze, as usually happens at peak business periods."

The trouble starts when the freeze is a date in someone's head rather than a written agreement. Projects with year-end deadlines try to squeeze in just before it starts, supplier deadlines and certificate renewals land in the middle of it, and anything that has to happen anyway gets labelled an emergency. The result can be more risk in December, not less.

## Practical steps

  1. Agree scope and dates with the business now. Name the services covered, the start and end dates and times, and any services that stay open for change because they are quiet over the holidays. Write it into your change policy or a short freeze notice, and get it signed off by the people who own those services.

  2. Define what is still allowed. Pre-approved standard changes with a proven procedure, security fixes for actively exploited vulnerabilities and fixes for major incidents are the usual exceptions. Everything else waits. Say who approves an exception during the freeze, and make sure that person is on the rota.

  3. Keep emergencies honest. A freeze tempts people to relabel planned work as urgent. John's warning applies directly: "Emergency changes should never be used as a proxy for an ‘urgent’ change, which simply implies a lack of planning." Log every exception, and review the list in January.

  4. Publish the change schedule early. John describes two purposes for the change schedule: "to prepare consumers for the impact of the change and to encourage anyone that may know of a reason why the change should not proceed to speak up". Show the pre-freeze rush, the freeze itself and the first weeks of January in one place, so clashes surface in November, not on 22 December.

  5. Check external dates. List supplier end-of-support dates, licence and certificate renewals, and vendor product switchovers that fall between now and mid-January. Bring forward what you can, and plan the rest as scheduled changes with named owners.

  6. Avoid the pre-freeze stampede. Set a cut-off for change requests about two weeks before the freeze, and do not let the last week before it become the busiest week of the year. A change pushed through to beat the deadline is often the one that fails over the holidays.

  7. Staff it like an incident. Agree on-call cover, escalation contacts and supplier support hours for every day of the freeze, including the bank holidays. A freeze reduces change; it does not stop incidents.

  8. Use the quiet time well. Documentation, knowledge articles, clearing old tickets, reviewing standard change procedures and tidying configuration records are all low risk and pay off in January.

## A short worked example

This is an illustrative example, not a real case. A regional housing association runs IT, facilities and HR services from one platform. In early November the change manager agrees a freeze from 19 December to 5 January covering the tenant portal, payroll and finance systems. Payroll has a run on 23 December, so payroll changes close on 5 December. The team finds that a supplier is retiring an old version of its integration on 31 December, so that upgrade is scheduled for 2 December with a tested remediation plan. During the freeze one exception is approved, a security patch, and it is logged. In January the team reviews the log, closes 140 stale tickets cleared during the quiet weeks and lifts the freeze one service at a time.

## Common mistakes

  1. Freezing everything for everyone, which pushes people to work around the process.
  2. Forgetting non-IT changes. HR, facilities and finance changes to shared systems need the same rules.
  3. No named approver for exceptions, so either nothing gets fixed or anything gets through.
  4. Ending the freeze with a big bang, where every postponed change goes in on the first Monday of January.
  5. Ignoring supplier changes made to your services during the freeze.

## Where this fits

This sits within change enablement, alongside release and service level management, and it applies well beyond IT. For more on ESM's Exchange, read using a change schedule to protect services and standard, normal and emergency changes, and share how your team handles the holidays in the Incident and problem space.

For the underlying good practice, see PeopleCert's ITIL guidance on change enablement and the service management standard ISO/IEC 20000.

If this helped, John Sansbury's The Journey to Service Excellence covers operational change, release policy and the change schedule in depth, and is available to Exchange members.