Treat "it has always worked" as a fact about the past, not a promise about today. Judge each routine change by what it could reach if it went wrong rather than by how often it has gone right, give it a tested remediation plan and a way to contain the damage, and review your pre-approved changes whenever anything around them changes.
## Why routine changes still cause big outages
Routine changes earn trust by repetition, and that trust slowly replaces thinking. The task stays the same, but the equipment, versions, suppliers and surrounding systems keep moving. When one of those shifts, a familiar job can behave in an unfamiliar way, and the damage can travel much further than anyone expected.
A public example came in November 2026. The US Federal Aviation Administration said a nationwide disruption followed "a routine replacement at a remote facility, which has regularly been done for decades", and that it would reconsider when it does such work. Its investigation was still going on when it said this, so the lesson here is about the pattern, not the root cause.
## Practical steps
-
Map what each routine change can reach. List your common routine changes and, for each, the services and components that depend on the thing being changed. John Sansbury puts the dependency plainly in The Journey to Service Excellence: "The ability to successfully manage operational changes is critically dependent on the maturity of service component management". If you cannot say what a router, server or integration connects to, you cannot judge the risk of touching it.
-
Separate frequency from risk. A change that is safe to pre-approve is low risk and well understood, not just frequent. John recommends handling pre-approved changes as service requests with a defined procedure, which only works if that procedure still matches reality.
-
Set triggers that end pre-approval. A new hardware model, a different supplier, a new software version or a change to the surrounding network should turn a routine change back into a normal change for its next run. So should any incident linked to it, until problem management has looked at the cause.
-
Contain the blast radius. Do the first site or system on its own, watch it for long enough to see trouble, and agree stop conditions before you start. Know in advance who can isolate the change and how quickly.
-
Make the remediation plan real. John's advice is that every normal and emergency change is tested and has a remediation plan before approval, and he notes: "This used to be called a back-out plan, but it is not always possible to back out of a change; sometimes it is necessary to move forwards." Write down the actual steps, and who carries them out, for both routes.
-
Choose the window by impact and by who will be awake. Quiet hours reduce the number of people affected, but they also reduce the number of people available to help. Doing everything at night can also slow essential upgrades badly, so be explicit about the trade off rather than defaulting to habit.
-
Put supplier work on your change schedule. Work by contractors and network providers on your services is still your change. It belongs on the same schedule.
## A short worked example
This is an illustrative example, not a real case. A college IT team replaces branch office switches as a pre-approved change and has done so dozens of times without trouble. The next batch comes from a different supplier and runs newer firmware. Under its trigger rule, the team treats the first replacement as a normal change. It tests the configuration in a lab, does one site first in a quiet window with the network lead on hand, watches traffic for two days against an agreed stop condition, then updates the written procedure. Only then does the change return to the pre-approved list, now describing the new model.
## Common mistakes
- Treating a success count as a risk assessment. Past success tells you the old conditions were safe, not the current ones.
- Pre-approving once and never revisiting. Standard changes need an owner and a review date.
- Rubber stamping approvals. John warns, "I am aware of enterprises where approval is just a tick-box exercise", which gives the appearance of control without reducing risk.
- Swinging to the opposite extreme. Sending every change to a large board feels safe, but John describes the efficiency cost of doing so, and it pushes people to work around the process.
- A remediation plan that just says "roll back". If nobody has tested the route back, or forward, it is a hope rather than a plan.
## Where this fits
This sits within change enablement, supported by configuration and problem management, and it applies well beyond IT. Facilities teams moving equipment and HR teams changing payroll or case management settings face the same pattern. For more on ESM's Exchange, read standard, normal and emergency changes and using a change schedule to protect services, and bring your own examples to the Incident and problem space.